Miacomet Pond is about a mile long and 46 acres, with a mean depth of just 4.8 feet. Its deepest point is 11 feet, near the southern end. Water from about 1,284 acres of surrounding land drains into that shallow basin. Under the water sits a thick layer of organic muck. By this point the pond was supposed to have pumps on it.
Dredging was scheduled to start in September 2026 and run through the fall and winter. It didn't start. Paperwork is no longer the obstacle, since the permits were finished more than a year ago. The holdup is cost. And because of the way those permits are written, a missed fall start costs the project far more than a few weeks.
What the Muck Is Doing Down There
The Town's Miacomet Pond Dredge Plan page states the problem plainly. For several summers in a row, the Town has had to limit swimming and other recreation on the pond because of harmful algal blooms, usually cyanobacteria, which can make people, pets and wildlife sick.
The algae feed on the bottom of the pond. Years of fertilizer and septic systems around the pond have built up nitrogen and phosphorus in the sediment, and that layer keeps leaching nutrients back into the water. Natural Resources Director Jeff Carlson explained the fix to the Nantucket Current with an analogy:
"It's like playing Nintendo in the old days. You'd get mad and hit the reset button and start over."
The idea has been around for a long time. Dredging to remove nutrients from the sediment was one of the conclusions of a 2005 study of the pond by then-town biologist Keith Conant. The Current called the project a first for the island: a test of whether dredging can actually improve Miacomet, and possibly a model for Nantucket's larger ponds. Carlson also described dredging as an alternative to alum treatment, the other common way communities bind excess nutrients.
Every Permit, in Order
The 2005 recommendation took two decades to reach the bidding stage because the project needed approvals at every level. Below Deck Nantucket listed the full sequence in March 2026:
| Approval | Issued by | Date |
|---|---|---|
| Order of Conditions | Nantucket Conservation Commission | July 2024 |
| Environmental Impact Report Certificate | MEPA | September 2024 |
| 401 Water Quality Certification | MassDEP | June 2025 |
| Chapter 91 Waterways Permit | Commonwealth of Massachusetts | July 2025 |
Money came during the same period. On July 23, 2024, the Town posted that it had won a $1 million grant from the Inland Dredging Pilot Round of the Massachusetts Dredging Program. The competition was tight. Requests totaled $14 million for $4 million in statewide funding.
By the end of the permit work, the plan called for removing about 80,000 cubic yards of nutrient-heavy sediment, and possibly as much as 135,000 cubic yards in total. The material would be pumped to the Surfside Wastewater Treatment Plant area for dewatering and processing. The Town's project page also mentions possible "beneficial reuse" of what comes out of the pond.
The Day the Bids Were Opened
The Town opened bids on April 3, 2026. Only two companies bid. According to Below Deck Nantucket's September report, Stage 3 Separation was the apparent low bidder at $16,598,034, and Robert B. Our Marine Division LLC bid $20,554,660.74.
Those numbers mean more next to the earlier ones. A 2023 Nantucket Land Bank project summary had put the rough cost at about $4 million. The Land Bank owns slightly more than half of the pond's shoreline and had already helped pay for planning and permitting. The low bid was more than four times that planning estimate. The two bids differed by about $3.96 million, which is nearly the size of the original estimate. The $1 million state grant covers about 6 percent of the low bid.
Below Deck pointed out that the $4 million was an early planning number and not necessarily the Town's final construction budget, and that Carlson did not say what the current budget is. The Town's bid sheet lists Stage 3 as the "apparent low bidder pending review," with the award field left blank.
On September 20, Below Deck published Carlson's confirmation:
"The Town will be releasing a larger update on this project in the next week or so. However, in short we will not be beginning dredging this fall due to the costs well exceeding the budget."
He added that the Town is "evaluating options and still wish[es] to proceed given permits in hand and the benefits to the pond."
Why a Missed Fall Costs So Much Time
The permits explain why this delay matters so much. Under the permit conditions, dredging is prohibited from April 1 through August 31 unless additional monitoring plans are approved. The restriction protects nesting shorebirds, including the Least Tern, and other seasonal use of the habitat around the pond. State review documents also describe construction as off-season work, partly to stay out of the way of peak public use.
That leaves a fall-to-early-spring window. The original schedule used it from the very start, with work beginning in September and running through fall and winter. Every month the project waits takes a month out of the current window, and the pause from April through August can't be used to make up the difference. Any choice the Town makes, whether a smaller scope, more funding, a different construction method or a new bid, which are the possibilities Below Deck listed, has to fit inside that calendar.
The cold-season timing raises a question of its own. In its March reporting, Below Deck noted that the permit conditions cover shorebirds, rare plants and wetland buffers in detail. They don't spell out protections for animals that spend the winter in the pond itself, such as painted and snapping turtles that go dormant in the bottom sediment, frogs, and the small invertebrates living in the muck that would be removed. Below Deck framed this as an open question and not as a flaw in the review. Whenever dredging does begin, it will still overlap those animals' dormant season.
The Pond This Winter
For now, the pond is unchanged, and the algae problem that started all this is still there. On October 5, 2026, the Inquirer and Mirror reported that every monitored island pond was under cautionary status. Concentrations were below the state's harmful-risk threshold but could still include harmful algae. Town officials advised cutting back on swimming and wading and choosing indirect activities like boating and kayaking.
The Town and its partners, which include the Nantucket Land Council, Nantucket Conservation Foundation, Nantucket Land Bank, Linda Loring Nature Foundation, UMass Boston and Mass Audubon, test the ponds weekly from June through early October. Testing has ended for the year, so the last posted signs reflect the pond as of early October. The colors mean the following:
- Green. Water activities are OK. Avoid drinking the water.
- Yellow. Use caution and reduce direct contact. Boating and kayaking are safer choices. Keep pets out of the water.
- Red. Stay out of the water entirely, and keep pets out too.
Most of the shoreline stays open year-round because more than half of it belongs to the Land Bank:
- Miacomet Pond. The Land Bank property is listed for kayaking, canoeing and hiking, with parking just past the golf course.
- Burchell Farm. Seventy acres along the northern half of the pond, with 2.3 miles of single-track trail running mostly north to south beside the water. It connects the Miacomet Avenue and Mizzenmast neighborhoods to Smooth Hummocks.
- Miacomet Woods. A shaded 0.8-mile forest trail across from the pond, with two pull-off parking spots at 70 Miacomet Road.
- Smooth Hummocks Coastal Preserve. Trails run south along the pond and join the preserve's dirt roads toward the south shore beaches.
The Land Bank asks pet owners on all four properties to follow local laws and clean up after their pets.
What to Watch Next
The work window means the important decisions come well before any equipment shows up. Here are the milestones to watch:
- The Town's larger update. Carlson said it would lay out the options. It's the first public explanation of how big the funding gap is, since he didn't give a budget figure in September.
- The award line on the bid sheet. Stage 3 Separation is still listed as apparent low bidder pending review. Either a contract award or a decision to rebid will show which way the Town is going.
- Any change in scope. The plan ranges from about 80,000 cubic yards up to roughly 135,000 cubic yards. If the Town shrinks the job to fit the money, the amount removed is the first thing that would change.
- The Land Bank's role in construction. It has already paid toward planning and permitting and expected to possibly help pay for the work itself.
- April 1. That's when the permit pause on dredging begins each year, and it runs through August 31.
The Town's project page has an email sign-up for updates, and Carlson's contact information is listed there.
Neighbors along Miacomet Avenue, Mizzenmast and West Miacomet Road have been hearing about this dredging project for years, and its schedule now depends on a seasonal calendar. If you'd like help understanding how projects like this one affect your corner of the island, John McGarr is happy to talk it through. If it's a good time to know where your home stands, you can start with a free home valuation.