Tom Nevers Road Gets Its Path This Winter, With a May Deadline in the Contract

October 29, 2026

The Town of Nantucket released its Invitation for Bids on the Tom Nevers Road Multi-Use Path on October 14, 2026. Contractors had an optional pre-bid conference yesterday, Wednesday, October 28. Sealed bids are due through the Town's e-Procurement Portal by 2 p.m. on Tuesday, November 17. The deadline matters most to anyone who drives, walks or bikes the road. Under the bid form, the winning contractor must have the whole project fully complete by May 28, 2027, and pays $1,000 in liquidated damages for every calendar day after that.

The Town has also said there will be no construction in the summer months. Between that rule and the May deadline, the path gets built in the months when Tom Nevers Road is at its quietest.

A Later Bid, an Earlier Finish

The Town showed abutters a schedule at a public information session on July 15, 2026. Since then, the start of the schedule has slipped and the end has moved earlier.

Milestone July 15 session October 14 bid documents
Bidding opens September 2026 October 14, 2026
Bids due Not stated November 17, 2026, 2 p.m.
Construction start Late fall 2026 Date set by a future Notice to Proceed
Summer work None Completion required before summer
Finish Target opening summer 2027 Fully complete by May 28, 2027

Bidding opened about a month later than the July timeline expected. Meanwhile the vague "summer 2027" target became a specific date three days before Memorial Day 2027, backed by a daily penalty. No contractor has been picked. Bids aren't due until mid-November, so the start date is still the Town's forecast. Whoever wins will have a building window that runs from whenever the Notice to Proceed arrives until late May.

The money was approved years ago. The Town says Annual Town Meetings authorized funding for design and construction in 2019 and 2025. Nantucket Current reported that a $14.5 million appropriation for a Tom Nevers bike path advanced at the 2025 Town Meeting, in a year when most borrowing articles missed the two-thirds threshold. That figure is what voters authorized. The construction price won't be known until bids come in.

What Goes in Along 2.05 Miles

The path runs 2.05 miles inside and along the Tom Nevers Road right-of-way, from the Milestone Road bike path to Tom Nevers Field. The July design calls for a 10-foot-wide path, mostly on the east and south side of the road. That side was chosen to cut down on conflicts with residential driveways. The path keeps a 4-foot safety offset from the roadway and is routed around existing utilities and poles. Those numbers replace an earlier state environmental review, dated December 2025, that described a 10- to 12-foot path with at least 5 feet of separation.

The bid scope covers selective demolition, the path itself, a raised boardwalk, roadway and driveway crossings, and grading and drainage. It also includes erosion and sediment controls, coordination of utility relocations, path signs and pavement markings, and loam, seeding and planting.

The design plans split the route into 11 sections. For anyone trying to work out which part of the road will be under construction near them, the sections run like this:

  1. Milestone Road to 6 Tom Nevers Road
  2. 6 Tom Nevers Road to 1 Longwood Drive
  3. 1 Longwood Drive to 9 Green Hollow Road
  4. 9 Green Hollow Road to 2 Lyons Lane
  5. 2 Lyons Lane to 9 Sandpiper Way
  6. 9 Sandpiper Way to 6 Flintlock Road
  7. 6 Flintlock Road to Old Tom Nevers Road
  8. Old Tom Nevers Road to 2 Lyford Road
  9. 2 Lyford Road to 98 Tom Nevers Road
  10. 98 Tom Nevers Road to 120 Tom Nevers Road
  11. 120 Tom Nevers Road to Tom Nevers Field

The bid documents don't say in what order the contractor will work through these sections. A May deadline with no summer work leaves little slack in any order.

The Boardwalk Stretch and the Easements

One short piece of the route explains why the project took years to reach bidding. About 343 feet of the corridor crosses Nantucket Land Bank property protected under Article 97, according to the December 2025 state environmental certificate included in the bid manual. The path crosses that land on a raised public boardwalk. The Town's project page still has an open discussion question about it. It asks whether a boardwalk over a low-lying conservation area is worth higher construction and maintenance costs. The project team says the path was designed to avoid wetland resource areas and to keep all work outside their buffer zones.

The rest of the route needs cooperation from neighbors. The state review found that the corridor touches about 37 privately owned properties, and said the Town was acquiring easements for them. A legal notice in The Inquirer and Mirror scheduled a County Commissioners public hearing on proposed temporary and permanent easements for Wednesday, July 22, 2026. The notice said trees, landscaping or other obstructions needed for construction and maintenance could be part of the taking. Abutters who want to see how their own frontage is drawn can find the Town's easement plan and 75 percent design drawings under supporting documents on the project page.

As for trees, the state review estimates that 10 public shade trees will come out and 10 will be replanted, with about 24 trees planted in total. The July presentation lists eastern red cedar, pitch pine, white oak and serviceberry as the planned species. Disturbed shoulders will be reseeded with native conservation mixes or low-maintenance turf.

Off-Season Work at the Far End of the Road Too

Tom Nevers Field and the park beyond it went through an off-season work schedule last winter. The Town's Tom Nevers Park debris removal project took out buried debris on the west side of the park, structures and debris on the beach, and material sticking out of the bluff face. Its first phase also built a beach access ramp for future DPW work. In a February 27, 2026 update, the Town said all major debris had been removed from the beach and water's edge, and that work had moved upland south of the former roller hockey rink. Crews were still clearing buried pockets there on March 13.

That ramp is still there, and the Town is clear that it's for DPW use only and isn't a public vehicle access point. It stays until the second phase of work meets the bluff face, and then it comes out and the area is revegetated.

Phase Two moves inland, removing buried debris from the main area of the park between the bunker and the bluff. The goal is to get it out before it ends up on the beach. Voters approved an $8 million debt exclusion for it in May 2026, by 304 to 116 at Town Meeting and 1,885 to 1,008 at the Annual Town Election. The Town says it is working on next steps and hasn't posted a schedule. If Phase Two follows Phase One's pattern, it would be more off-season work at the Field end of the road. For now the only dated project on Tom Nevers Road is the path.

Dates to Watch From Here

  • November 17, 2026, 2 p.m.: bids close on the OpenGov portal under Project 2026-DPW-1007.
  • Notice to Proceed: this sets the real construction start date. The Tom Nevers path project page has an email sign-up for updates.
  • Questions about your section: the listed contact is Mike Burns, Transportation Program Manager with the Nantucket Planning & Economic Development Commission, at [email protected].
  • May 28, 2027: the contract completion deadline, before the summer months when the Town has said no construction will take place.
  • Phase Two debris removal: watch for an announcement on the Tom Nevers Park debris removal page.

Easement terms and contract provisions come from the Town's own documents. This post is general information and not legal advice, so abutters with questions about their own property should talk to the Town and their own attorney.